Contents
Breaches of Action and Limit Levels
for Air Quality
Breaches of Action and Limit Levels
for Noise
Breaches of Action and Limit Levels
for Water Quality
Soft Shore Ecological Monitoring
Environmental Complaints,
Non-compliance & Summons
Key Issues For The Coming Month
1.4 SUMMARY OF CONSTRUCTION WORKS
1.5 SUMMARY OF EM&A PROGRAMME REQUIREMENTS
1.6 STATUS OF STATUTORY ENVIRONMENTAL COMPLIANCE WITH THE ENVIRONMENTAL
PERMIT
1.7 STATUS OF OTHER STATUTORY ENVIRONMENTAL REQUIREMENTS
2.
EM&A RESULTS FOR TUNG
CHUNG EAST.
2.1.1 Monitoring Requirements and
Equipment
2.1.2 Monitoring Schedule for the
Reporting Month
2.1.3 Results and Observations
2.2.1 Monitoring Requirements and
Equipment
2.2.2 Monitoring Schedule for the
Reporting Month
2.2.3 Results and Observations
2.4 COMPENSATION WOODLAND MONITORING
2.5 PRESERVED/TRANSPLANTED PLANT SPECIES OF CONSERVATION IMPORTANCE
MONITORING
2.5.1 Preserved Plant Species of
Conservation Importance
2.5.2 Transplanted Plant Species of
Conservation Importance
2.7 Soft Shore Ecological Monitoring
2.10 LANDSCAPE
AND VISUAL MONITORING
2.11 IMPLEMENTATION
STATUS OF ENVIRONMENTAL MITIGATION MEASURES
2.12 SUMMARY
OF COMPLAINTS, NOTIFICATION OF SUMMONS AND SUCCESSFUL PROSECUTIONS
3.1 Construction Programme for the Coming Month
3.2 MONITORING SCHEDULE FOR THE COMING MONTH
4.
CONCLUSION AND RECOMMENDATION
ANNEX b Environmental Mitigation Implementation Schedule
ANNEX c Status of Submissions and Implementation Status of
Mitigation Measures under EP
ANNEX d Status of Statutory Environmental Requiremens
ANNEX e1 Calibration Certificates for Air Quality
ANNEX e2 Monitoring Schedule for Air Quality
ANNEX e3 Monitoring Results for Air Quality
ANNEX e4 Event and Action Plan for Air Quality
ANNEX f1 Calibration Certificates for Noise
ANNEX f2 Monitoring Schedule for Noise
ANNEX f3 Monitoring Results for Noise
ANNEX f4 Event and Action Plan for Noise
ANNEX g Compensation Woodland Monitoring
ANNEX h Preserved/Transplanted Plant Species of Conservation
Importance Monitoring
ANNEX h1 Preserved Plant Species of Conservation Importance
ANNEX h2 Transplanted Plant Species of Conservation Importance
ANNEX i Eco-shoreline Monitoring
ANNEX J Landscape and Visual Monitoring
ANNEX J1 Examples of Landscape and Visual Mitigation Measures
ANNEX J2 Event and Action Plan for Landscape and Visual
Mitigation Measures
ANNEX L Monitoring Schedule for the Next Reporting Period
List of Tables
Table 1.1..... Contact
Information of Key Personnel
Table 1.2..... Major
Activities in the Reporting Period
Table 1.3..... Summary
of Status for the Environmental Aspects under the Updated EM&A Manual
Table 2.1..... Action
and Limit Levels for 1-hour TSP
Table 2.2..... Air
Quality Monitoring Details
Table 2.3..... Summary
of 1-hour TSP Monitoring Results in the Reporting Period
Table 2.4..... Action
and Limit Levels for Construction Noise
Table 2.5..... Noise
Monitoring Details
Table 2.6..... Summary
of Construction Noise Monitoring Results in the Reporting Period
Table 2.7..... KEY Observations Identified during the Site
Inspection in this Reporting Month
Table 2.8..... QUANTITIES OF Different Waste Generated and Imported Fill
Materials
Table 2.9..... IMPLEMENTATION STATUS of Landscape and Visual Mitigation
Measures
Table 2.10 ... MONITORING Programme for Landscape and Visual
Table 3.1.....
Major Activities for the Next Reporting Period
LIST OF FIGURES |
|
Acronyms and abreviations
Acronyms |
Description |
C&D |
Construction and Demolition |
CAP |
Contamination Assessment Plan |
CEDD |
Civil Engineering and Development Department |
CWD |
Chinese White Dolphin |
DCM |
Deep Cement Mixing |
DO |
Dissolved Oxygen |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
EIS |
Ecologically Important Stream |
EM&A |
Environmental Monitoring and Audit |
EP |
Environmental Permit |
EPD |
Environmental Protection Department |
ER |
Engineer's Representative |
ERM |
ERM-Hong Kong, Limited |
ET |
Environmental Team |
HVS |
High Volume Sampler |
IEC |
Independent Environmental Checker |
PDA |
Planned Development Area |
PME |
Powered Mechanical Equipment |
QPME |
Quality Powered Mechanical Equipment |
RAP |
Remediation Action Plan |
RR |
Remediation Report |
RTTM |
Real Time Tracking and Monitoring |
SS |
Suspended Solid |
TCB |
Tung Chung Bay |
TCE |
Tung Chung East |
TCNTE |
Tung Chung New Town Extension |
TCW |
Tung Chung West |
The Project |
Tung Chung New Town Extension (East) |
THW |
Tai Ho Wan |
TSP |
Total Suspended Particulate |
Updated EM&A Manual |
Updated Environmental Monitoring and Audit Manual for Tung Chung New Town Extension prepared by ERM under Agreement No. CE 60/2017 (EP) and deposited to EPD under Environmental Permit No. EP-519/2016 |
Tung Chung New Town Extension
(TCNTE) is one of the major initiatives under the Government's multi-pronged
approach to increase land supply to meet Hong Kong's medium- to long-term needs
for housing, economic and social developments. The Environmental Impact
Assessment (EIA) Report for TCNTE (Register No. AEIAR-196/2016) was approved on
8 April 2016 and the Environmental Permit (EP) No. EP-519/2016, covering the
construction and operation of TCNTE, was granted on 9 August 2016. The
EIA Report and EP cover both Tung Chung East (TCE) and Tung Chung West
(TCW). ERM-Hong Kong, Limited (ERM) is commissioned to undertake the role
of Environmental Team (ET) for the construction and operation of TCE Project
(“the Project”) in accordance with the requirements specified in the EP,
Updated Environmental Monitoring and Audit (EM&A) Manual, EIA Report of the
TCNTE project and other relevant statutory requirements.
The construction of the Contract
No. NL/2017/03 - Tung Chung New Town Extension –
Reclamation and Advance Works (“Contract 1”) at TCE commenced on 9 July
2018.
The construction of the Contract
No. NL/2020/02 - Tung Chung New Town Extension – Salt Water
Supply System (“Contract 2”) at TCE commenced on 4 September 2021.
The construction of the Contract
No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in
Tung Chung East (“Contract 3”) at TCE commenced on 5 November 2021.
The construction of the Contract
No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (“Contract
7”) at TCE commenced on 15 March 2022.
This is the Monthly EM&A report
presenting the EM&A works carried out during the period from 1 to 31 August
2024 for the TCE Project in accordance with the Updated EM&A Manual.
A summary of monitoring and audit
activities conducted in the reporting period is listed below:
Air Quality
Monitoring
5 sessions
Noise
Monitoring
5 sessions
Preserved Plant Species
Monitoring 1
session
Transplanted Plant Species Monitoring
1 session
Environmental
Site Inspection
·
Contract
1
2 sessions
·
Contract
2
4 sessions
·
Contract
3
5 sessions
·
Contract
7
4 sessions
Environmental
Management Meeting
·
Contract
2
1 session
·
Contract
3
1 session
·
Contract
7
1 session
Environmental auditing works,
including weekly site inspections of construction works conducted by the ET,
audit of implementation of Complaint Management Plan, Eco-shoreline
Implementation Plan, Detailed Preservation and/or Translocation of Plant Species
of Conservation Importance, Detailed Compensatory Woodland Planting Plan and Waste Management Plan
were conducted in the reporting period. Based on the audit results and
the observation for the reporting period, environmental pollution control and
mitigation measures for the Project were properly implemented.
No exceedance of Action and Limit
Levels was recorded for construction air quality monitoring in the reporting
period.
No exceedance of Action/Limit
Levels was recorded for construction noise monitoring in the reporting
period.
Water quality monitoring was
suspended in the reporting period.
The construction of vertical
eco-shoreline, mangrove eco-shoreline and rocky eco-shoreline has been
substantially completed. Wet season monitoring
was conducted during the reporting period.
There was no notification of
summons or prosecution recorded in the reporting period.
One (1)
environmental complaint related to Contract 2 and Two (2) environmental
complaints related to Contract 3 were received in the reporting
period. Investigations were conducted for the environmental complaint in
accordance with the complaint handling process as stated in the Complaint
Management Plan.
There
was no reporting change in the reporting period.
Potential environmental impacts
arising from the upcoming construction activities in the next reporting period
of September 2024 are mainly associated with dust emission, noise from plant
operation during normal working hours and restricted hours, handling and
storage of C&D materials generated from construction activities, efficiency
of wastewater and drainage management and tree protection. The ET will
keep track on the construction works to confirm compliance of environmental
requirements and the proper implementation of all necessary mitigation
measures. The ET will also recommend to the Contractor about the
environmental toolbox tofpics on the abovementioned
key issues for the coming month.
Tung Chung New Town Extension
(TCNTE) is one of the major initiatives under the Government's multi-pronged
approach to increase land supply to meet Hong Kong's medium- to long-term needs
for housing, economic and social developments. The Environmental Impact
Assessment (EIA) Report for TCNTE (Register No. AEIAR-196/2016) was approved on
8 April 2016 and the Environmental Permit (EP) No. EP-519/2016, covering the
construction and operation of TCNTE, was granted on 9 August 2016. The EIA
Report and EP cover both Tung Chung East (TCE) and Tung Chung West (TCW).
ERM-Hong Kong, Limited (ERM) is
commissioned to undertake the role of Environmental Team (ET) for the
construction and operation of TCE Project (“the Project”) in accordance with
the requirements specified in the EP, Updated Environmental Monitoring and Audit
(EM&A) Manual ([1]),
EIA Report of the TCNTE project ([2])
and other relevant statutory requirements.
The TCNTE
comprises the following elements:
(a) TCE
Project
1. Reclamation of the seabed
by a non-dredged method at TCE to form a total of about 130 hectares of land;
2. Construction of about
4.9 kilometers of seawalls, with an eco-shoreline,
three drainage box culvert outfalls, three circulation drains and a seawater
intake at TCE;
3. Provision of
infrastructure for Tung Chung Area 58, including construction of a single
two-lane road with a footpath and the associated utility works;
4. Construction of
proposed open space;
5. Construction of roads,
footpaths, cycle tracks and the associated junction / road improvement works;
6. Engineering
infrastructure works covering drainage, sewerage, waterworks (including a fresh water service reservoir, a salt water service
reservoir and a salt water pumping station), common utility tunnels and
landscaping works; and
7. Implementation of
environmental mitigation measures and environmental monitoring and audit
programme for the works.
(b) TCW
Project
1. Site formation works at TCW;
2. Construction of proposed
open space;
3. Construction of the River
Park including a visitor centre at TCW; and
4. Construction of sustainable urban drainage
systems at TCW.
The locations of Contracts 1, 2,
3 and 7 are shown in Figure
1.1 to 1.4. The construction and the reclamation related marine
works of Contract 1 commenced on 9 and 13 July 2018, respectively. The
construction of Contracts 2, 3 and 7 commenced on 4 September 2021, 5 November
2021 and 15 March 2022, respectively.
This is the Monthly EM&A
Report for the TCE Project which summarises the key
findings of the EM&A programme during the
reporting period from 1 to 31 August 2024 for the construction works.
The
organization structure of the Project is shown in Annex A. The key
personnel contact names and contact details are summarized in Table 1.1
below.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Environmental Team (ET) (ERM-Hong Kong, Limited) |
ET Leader |
Kelvin So |
3894 9504 |
Deputy ET Leader |
Raymond Chow |
2271 3281 |
|
Independent Environmental Checker (IEC) (Binnies Hong Kong Limited) |
IEC |
Manuel Chua |
3894 9807 |
Deputy IEC |
Edward Lau |
3894 9695 |
|
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
|||
Civil Engineering and Development Department |
Marine Conservation Officer |
Wo King Tai |
3894 9707 |
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Chief Resident Engineer |
Chris Cheung |
3894 9604 |
|
Resident Engineer |
Victor Chan |
3894 9666 |
|
Inspector of Works |
Clement Fan |
3894 9798 |
|
Contractor (Build King – SCT Joint Venture)
|
Site Agent |
David Wong |
9653 8635 |
Civil Division Head |
Marco Chan |
9257 7033 |
|
Environmental Officer |
Issac Wong |
9873 8968 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
|||
Civil Engineering and Development Department |
Senior Engineer |
Patrick C Y Yeung |
2231 4435 |
Electrical & Mechanical Engineer |
Samson K L Yip |
2231 4460 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Senior Resident Engineer |
Sunny Ng |
3894 9605 |
|
Senior Resident Engineer |
Vincent Leung |
3894 9645 |
|
Resident Engineer |
Amen Fung |
3894 9676 |
|
Senior Inspector of Works |
Wong Ting Yu |
3894 9706 |
|
Contractor (China Geo-Engineering Corporation)
|
Construction Manager |
Ambrose Kwong |
6198 7787 |
Site Agent |
Edward Mok |
6498 4306 |
|
Construction Team Leader |
C K Chung |
5401 5720 |
|
Environmental Officer |
Fung Ka Bao |
9120 1489 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
|||
Civil Engineering and Development Department
|
Senior Engineer |
Eddie W C Lam |
2231 4445 |
Senior Engineer |
Phoebe Tang |
2231 4423 |
|
Engineer |
Timothy H M Chan |
2231 4473 |
|
Engineer |
Colin K C Wong |
2231 4417 |
|
Engineer |
Wing Chen |
3894 9704 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Chief Resident Engineer |
Gloria Tang |
3894 9639 |
|
Senior Resident Engineer |
Winston Wong |
3894 9650 |
|
Resident Engineer |
David Li |
3894 9684 |
|
Resident Engineer |
Alvis Li |
3894 9558 |
|
Resident Engineer |
Anson Yip |
3894 9559 |
|
Senior Inspector of Works |
Douglas Ng |
3894 9737 |
|
Contractor (Build King Civil Engineering Limited)
|
Construction Manager |
Cheung Siu Lun |
2272 3680 |
Site Agent |
Paul Lui |
9095 7922 |
|
Deputy Site Agent |
Aldous Lo |
9225 0368 |
|
Construction Team Leader |
Ken Yau |
9197 2219 |
|
Environmental Officer |
Tim Lin |
6390 0018 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
|||
Civil Engineering and Development Department |
Senior Engineer |
Phoebe Tang |
2231 4423 |
Engineer |
S H Leung |
2231 4449 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited) |
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Senior Resident Engineer |
Kelvin Kwan |
3894 9641 |
|
Senior Resident Engineer |
Brian Li |
3894 9556 |
|
Resident Engineer |
Kingsley Ho |
3894 9552 |
|
Resident Engineer |
Jessie Tang |
3894 9678 |
|
Senior Inspector of Works |
C K Liu |
3894 9733 |
|
Contractor (Build King Civil Engineering Limited) |
Site Agent |
Hon Yee |
9090 3109 |
Deputy Site Agent |
Vincent Kwan |
9833 1313 |
|
Construction Team Leader |
Vincent Lo |
9883 9229 |
|
Environmental Officer |
Nash Wong |
9810 1946 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
As informed by
the Contractor, details of the major works carried out in this reporting period
are listed below:
Table 1.2 Major
Activities in the Reporting Period
Activities |
Key Issues |
Key Mitigation Measures |
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
||
Land-based Works |
||
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Potential surface runoff · Noise from plant operation during normal working hours or restricted hours · Dust emission during storage and transfer of sand/ sorted public fill |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Strictly follow requirement under CNP for the use of PMEs and works within restricted period · Use of acoustic mat and other noise mitigation measures when necessary · Regular maintenance of engines and mechanical equipment |
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
||
Land-based Works |
||
· Construction of pumping station at Portion 6 · Construction of Intake Culvert at Portion 6 · Construction of service reservoir, TMF mainlaying at Portion 3 · Construction of HDD works at Portion 3 · CLP cable duct laying works at Wong Lung Hang at Portion 3 · Watermain laying works at Portion 3 along Man Tung Road, Tung Chung Road, and inside WSD facilities · Watermain laying works at Yi Tung Road at Portion 4 · Manhole construction and pipe laying for drainage works at Portion 5A · Construction of T-Junction in Yi Tung Road at Portion 5
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works
|
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
||
Land-based Works |
||
· Excavation and ELS works at Portion 104 · Excavation and ELS works at CUT no.1, 2, 3, 4 and supporting building · Construction works for CUT no. 1 structure · Back-filling works for CUT 2 · Construction works and furniture installation of PM office at WA9 · Construction works of Contractor office at WA6 · Drainage, Sewerage and watermain works at Road L4, L3, L5 and Portion 16 · DCS works at Road L4 and L3. · Pipe laying works for twin rising mains/ watermain laying at Man Tung Road · Preparation and pipe jacking works at Ying Tung Road · Pipe jacking works at Yi Tung Road · Foundation and backfilling works for noise barrier at Portion 11 · Road and drainage works in Road P1 · Road widening works at Ying Hei Road · Road D4, Road L7, ELS installation |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management
|
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
||
Land-based Works |
||
· Open cut excavation, backfilling and pipe laying for rising main and watermain at Portion 146-1 to 146-5 · Laying subbase and asphalt for temporary haul road along 146-1 to 146-14 · Pak Mong bridge I-beam erection, insitu construction of abutment and diaphragm · Trench excavation and pipe laying works at Portions 32 (Sham Shui Kok Drive) and Portion 38 · Trench excavation and pipe laying works at Portion 32 (Access Road adjacent to MTRC Siu Ho Wan Depot) · Establishment of pipe jacking works at Portion 33 · Horizontal grouting at Receiving pit at Portion 32 · RC construction of Retaining Wall FR1 · Pak Mong Subway Extension Phase 1 Temporary Pedestrian Diversion · Preparation works for falsework at casting yard A1 and A2 · ELS at A1a and A2b · RC for RW-R1, RW-R2, RW-R3 and RW-R4 at Portion 146-2 to 146-4 · RC construction at RW-R7 at Portion 31 · RC works at Wall E · Mini-piles at Wall D · Bored piles at Bridge C at Portion 146-12 · U channel and chain link fence construction at Portion 147-1 and 147-2 · Site clearance and tidiness |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
The environmental mitigation implementation
schedule is presented in Annex
B.
The status for
all environmental aspects is presented in Table 1.3. The EM&A
requirements remained unchanged during the reporting period.
Table 1.3 Summary
of Status for the Environmental Aspects under the Updated EM&A Manual
Parameters |
Status |
|
Air Quality |
||
Baseline Monitoring |
The results of baseline air quality monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going for TCE, monitoring conducted three times every six days |
|
Noise |
|
|
Baseline Monitoring |
The results of baseline noise monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going for TCE, monitoring conducted once per week |
|
Impact Monitoring for Road Traffic Noise during Operational Phase |
To be conducted during operational phase |
|
Fixed Noise Commissioning Test |
To be implemented by the Contractor before operation of TCNTE |
|
Water Quality |
|
|
Baseline Monitoring |
The results of baseline water quality monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
Suspended for TCE with approval from EPD |
|
Waste Management |
|
|
Waste Monitoring |
On-going |
|
Land Contamination |
|
|
Contamination Assessment Plan (CAP), Remediation Action Plan (RAP) and Remediation Report (RR) |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Ecology |
|
|
Monitoring for Compensation Woodland
|
Compensation Woodland Planting was completed on 30 September 2022 On-going, monitoring conducted quarterly |
|
Monitoring for Emergent Plant inside the future River Park |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Monitoring for Translocated Amphibians of Conservation Importance |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Monitoring for Preserved/Transplanted Plant Species of Conservation Importance
|
On-going, for preserved plant species, monitoring conducted once per month; for transplanted plant species, replacement planting was carried out on 28 April 2023 and 19 September 2023. Monitoring conducted once per month for the first year, and quarterly for the second year. |
|
Monitoring for Tung Chung Stream EIS and Wong Lung Hang EIS
|
To be conducted under TCW. Refer to the EM&A Reports of TCW. Monitoring for Wong Lung Hang was not required and the proposal was accepted by EPD on 2 September 2021 |
|
Eco-shoreline Monitoring |
The dry season monitoring between December 2023 and February 2024 was completed. Wet season monitoring was in progress. |
|
Tung Chung Bay and Tai Ho Wan Baseline Monitoring |
The results of baseline soft shore ecological monitoring at Tung Chung Bay and Tai Ho Wan were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Tung Chung Bay and Tai Ho Wan Impact Monitoring |
Completed |
|
Tung Chung Bay and Tai Ho Wan Post-construction Monitoring |
On-going for TCE, monitoring conducted quarterly |
|
Landscape and Visual |
|
|
Baseline Monitoring |
The results of baseline landscape and visual monitoring were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going |
|
Site Environmental Audit |
|
|
Regular Site Inspection |
On-going |
|
Dolphin Watching Plan implementation measures |
Completed |
|
Works Vessel Travel Route Plan implementation measures |
Completed |
|
Silt Curtain Deployment Plan implementation measures |
All silt curtain was removed in accordance with the Silt Curtain Deployment Plan and after obtaining the acceptance from EPD |
|
Spill Response Plan implementation measures |
Completed |
|
Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance implementation measures |
Under implementation by the Contractor of Contract 2 |
|
Detailed Compensatory Woodland Planting Plan implementation measures |
Under implementation by the Contractor of Contract 2 |
|
Waste Management Plan implementation measures |
Under implementation by the Contractor of Contract 1, 2, 3 and 7 |
|
Complaint Hotline and Email Channel |
Under implementation by the Contractor of Contract 1, 2, 3 and 7 |
|
Environmental Log Book |
On-going |
|
Taking into account
the construction works, impact monitoring of air quality, noise and waste
management were carried out in the reporting period. The monitoring
schedule of air quality and noise are provided in Annex E2 and Annex F2 respectively.
The EM&A programme also involved environmental site inspections and
related auditing conducted by the ET for checking the implementation of the
required environmental mitigation measures recommended in the approved EIA
Report and relevant EP submissions, including Complaint Management Plan,
Eco-shoreline Implementation Plan, Detailed Preservation and/or Translocation
Plan for Plant Species of Conservation Importance, Detailed Compensatory
Woodland Planting Plan and Waste Management Plan.
To promote the
environmental awareness and enhance the environmental performance of the
contractors, environmental trainings and regular environmental management
meetings were conducted during the reporting period, which are summarized as
below:
•
Three (3) environmental management committee meetings were held among
the relevant contractors, ER, ET, IEC and CEDD on 21, 14 and 13 August 2024 for
Contracts 2, 3 and 7;
•
Environmental toolbox trainings on loading, unloading and transfer of
material, removal of stagnant water & preventation
of mosquito breeding on 6 and 20 August 2024 were conducted for Contract 2;
• Environmental toolbox trainings on backfilling, deposition and compaction of fill material, scaffolding, shotcreting, percussive piling, bored piling, mini piling, steel works, anti-mosquitos control measures, chemical waste and handling of chemical spillage on 1, 6, 8, 13, 15, 20, 22, 27 and 29 August 2024 were conducted for Contract 3;
•
Environmental toolbox trainings on protection and preservation of trees,
ground investigation, site clearance, formwork and falsework on 7, 14, 21 and
28 August 2024 were conducted for Contract 7.
The status of
statutory environmental compliance with the EP conditions under the EIAO,
submission status under the EP and implementation status of mitigation measures
are presented in Annex C.
The
environmental licenses and permits, including environmental permit, discharge
license under Water Pollution Control Ordinance, registration as chemical waste
producer, construction noise permit and specified processes license, which were
valid in the reporting period are presented in Annex D. No non-compliance with environmental statutory
requirements was recorded.
According to
the Updated EM&A Manual of the Project, impact air quality monitoring in
terms of 1-hour Total Suspended Particulate (TSP) was conducted three (3) times
every six (6) days when the highest dust impact was expected. The Action
and Limit Levels of the air quality monitoring is provided in Table 2.1
below.
Table 2.1 Action
and Limit Levels for 1-hour TSP
Location |
Action Level (µg/m3) |
Limit Level (µg/m3) |
Monitoring station for Tung Chung East |
279 |
500 |
Portable direct reading dust meters were used
to measure 1-hour TSP levels in undertaking the air quality monitoring for the
Project. The proposed use of portable direct reading dust meters was
submitted to IEC and obtained agreement from the IEC as stated in Section 5.5
of the Updated EM&A Manual. With the use of direct reading dust
meter, it can allow prompt and direct results for the EM&A reporting and
the implementation of the event and action plan. The portable direct
reading dust meter would be calibrated every year against High Volume Sampler
(HVS) to check the validity and accuracy of the results measured by direct
reading method.
The monitoring
location and equipment used in the impact air quality monitoring programme are summarized in Table 2.2 and
illustrated in Figure 2.1.
Copies of the calibration certificates for the equipment are presented in Annex E1, which showed that
the portable direct reading dust meter is capable of providing comparable
results with that provided by a HVS.
Table 2.2 Air
Quality Monitoring Details
Monitoring Station |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
DM-1 |
Tung Chung Area 56 – Ying Tung Estate |
1-hour TSP |
Three times per six days during the construction period of the Project |
3, 9, 15, 21 and 27 August 2024 |
1-hour TSP Dust Meter SIBATA LD-3B (S/N: 436553) |
Note: It
should be noted that impact monitoring at other construction dust monitoring
locations at TCE as stated in the Updated EM&A Manual will commence after
the flat intake (for Monitoring Stations DM-2, DM-3 and DM-4).
The schedule
for air quality monitoring during the reporting period is provided in Annex E2.
The monitoring
results for 1-hour TSP are summarized in Table 2.3. The monitoring
data and the graphical presentation are provided in Annex E3.
Table 2.3 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
Monitoring Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
DM-1 |
48 |
39-55 |
279 |
500 |
Major dust sources in the reporting period
included haul road traffic and excavation under the Project.
No exceedance
of Action and Limit Levels was recorded for construction air quality monitoring
in the reporting period. No action was thus required to be undertaken in
accordance with the Event and Action Plan presented in Annex E4.
According to
the Updated EM&A Manual of the Project, impact noise monitoring was
conducted once per week during the construction phase of the Project. The
Action and Limit Level for construction noise of the Project is provided in Table
2.4 below.
Table 2.4 Action
and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700 - 1900 hours on normal weekdays |
When one documented complaint is received |
75 dB(A) a, b |
Note:
a
Limit level is exceeded when Leq ≥
75 dB(A). If works are to be carried out during restricted hours, the
conditions stipulated in the construction noise permit issued by the Noise
Control Authority have to be followed.
b Reduce to 70 dB (A) for schools and 65 dB (A) during school examination
periods.
Noise monitoring was performed using
sound level meter at the designated monitoring stations NMS-CA-1A ([3]) ([4])
and NMS-CA-4 (Figure 2.2;
Table 2.5) in accordance with the requirements stipulated in the Updated EM&A Manual. Acoustic calibrator
was deployed to check the sound level meters at a known sound pressure
level. Details of the deployed equipment are provided in Table 2.5.
Copies of the calibration certificates for the equipment are presented in Annex F1.
Table 2.5 Noise
Monitoring Details
Monitoring Station a |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
NMS-CA-1A b |
Residential premise in Tung Chung East – Century Link/Ying Hong Road c |
30-minute measurement between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded. |
Once per week for 30 mins during the construction period of the Project |
3, 9, 15, 21 and 27 August 2024 |
Sound Level Meter: Rion NL-52 (S/N: 00331805)
Acoustic Calibrator: LARSON DAVIS CAL200 (S/N: 16172) |
NMS-CA-4 |
Residential premise in the reclamation area next to Tung Chung East – Ying Tung Estate |
Note:
a
It should be noted that impact monitoring at other construction
noise monitoring locations at TCE as stated in the Updated EM&A Manual will
commence after the flat intake of residential premise in TCE (for Monitoring
Station NMS-CA-1) and operation of schools (for Monitoring Stations NMS-CA-2
and NMS-CA-3).
b
Impact monitoring at monitoring station NMS-CA-1A commenced on 19
September 2018 in view of the close vicinity of the construction works near the
residential area at Century Link.
c
Due to land handover issue, NMS-CA-1A was relocated to Ying
Hong Road which is located 60m away from the original location. Proposal
on the relocation of NMS-CA-1A was approved by IEC on 23 November 2018.
Noise monitoring at the relocated location commenced since 24 November 2018.
The schedule
for noise monitoring during the reporting period is provided in Annex F2.
Results for
noise monitoring are summarized in Table 2.6. The monitoring data
and the graphical presentation are provided in Annex F3.
Table 2.6 Summary
of Construction Noise Monitoring Results in the Reporting Period
Monitoring Station |
Average, dB(A), |
Range, dB(A), Leq (30mins) |
Limit Level, dB(A), Leq (30mins) |
NMS-CA-1A |
65.6 |
64.5-67.5 |
75 |
NMS-CA-4 |
68.2 |
65.6-69.9 |
75 |
Major noise sources during the noise
monitoring included noise from plant operation, craning, piling, haul road
traffic, nearby traffic and aircraft as well as nearby construction
sites.
No
Action/Limit Level exceedance was recorded for construction noise monitoring in
the reporting period. No action was thus required to be undertaken in
accordance with the Event and Action Plan presented in Annex F4.
No
monitoring event for impact water quality monitoring was conducted at all
designated monitoring stations during the reporting period. Water quality
monitoring has been suspended since 3 October 2023 as all reclamation works and
marine construction activities have been completed.
Compensation woodland planting
under Contract 2 was completed on 30 September 2022. With the approval
from EPD on the monitoring proposal in August 2023, quarterly
post-planting monitoring for compensation woodland was commenced in September
2023. No compensation woodland monitoring was carried out in the
reporting month. Photographic record of the compensation woodland
planting is provided in Annex
G.
Plant species
of conservation importance, including three individuals of Aquilaria
sinensis and 33 individuals of Gmelina chinensis, were identified
within works areas for Contract 2 during the survey conducted in August
2021. All individuals of Aquilaria sinensis and 31 individuals of Gmelina
chinensis were recommended being preserved in-situ
while two individuals of Gmelina chinensis (RT-07 and RT-08) were
recommended being transplanted to the receptor site in accordance with the
Detailed Preservation and/or Translocation Plan for Plant Species of
Conservation Importance approved under Condition 2.21 of EP-519/2016.
Initial tree
survey was conducted in September 2021 under Contract No. NL/2020/02 before the
commencement of construction works. According to the initial tree survey
conducted, the in-situ preserved plant species of conservation
importance of which one individual of Aquilaria sinensis and six
individuals of Gmelina chinensis were found missing.
During the monthly monitoring of
the in-situ preserved plant species of conservation importance in
November 2023, one individual of Aquilaria sinensis and one individual
of Enkianthus quinqueflorus
were newly observed and recommended being preserved in-situ.
Registration and measurement for two additional trees were conducted on 4
December 2023.
Monthly
monitoring of the in-situ preserved plant
species of conservation importance by the Qualified Personnel (QP)
appointed under Contract 2 was implemented in the reporting period.
Health condition was considered fair for the majority of
the in-situ preserved plant species of conservation importance, of which
two individuals of Gmelina chinensis could not be monitored as a result
of unsafe access to the locations, as recorded during the monitoring carried
out on 27 August 2024.
Tree protection
zones for the in-situ preserved plant species of conservation importance
were demarcated. No injuries and/or damages to the individuals of the in-situ
preserved plant species of conservation importance were reported by the QP
since the previous monitoring events. Photographic record and tree
schedule of the preserved plant species of conservation importance monitoring
are provided in Annex H1.
The ET will
continue to monitor the implementation of monitoring of in-situ
preserved plant species of conservation importance.
Site visit to
the receptor site for the transplanted plant species of conservation importance
under Contract 2 was carried out on 20 January 2022 prior to the commencement
of transplantation works for the transplanted plant species of conservation
importance on 21 January 2022.
The
transplanted plant species of conservation importance were both certified as
dead trees by the QP on 15 June 2022 as no living signs were observed.
Replacement planting of new trees of the same species, or other species to the
satisfaction of the Project Manager, at the Contractors’ expense would be
deemed necessary in accordance with the conditions under the approved Detailed
Preservation and/or Translocation Plan for Plant Species of Conservation
Importance. Replacement planting of three (3) Aquilaria sinensis
were completed on 28 April 2023. One (1) individual was certified dead by
the QP as no living signs were observed on 26 July 2023. The removal of
the dead tree and replanting of one (1) individual of Aquilaria sinensis
were completed on 19 September 2023.
The
establishment period of two (2) individuals of Aquilaria sinensis was
ended on 27 April 2024 and quarterly monitoring will be conducted in October
2024.
Monthly monitoring of
the replacement planting of one (1) individual Aquilaria sinensis was
carried out on 22 August 2024 and it was in fair health condition. Photographic record and tree schedule
of Aquilaria sinensis monitoring are provided in Annex H2.
The
transplanted plant species of conservation importance were watered twice a week
during the establishment period to keep the soil moist except in days with
heavy rainfall. The ET will continue to monitor the implementation of
monitoring of in-situ preserved/ transplanted plant species of conservation
importance.
The
construction of vertical eco-shoreline, mangrove eco-shoreline and rocky
eco-shoreline has been substantially completed. Photographic record is
provided in Annex
I.
The 1st Progress report
of the eco-shoreline monitoring was submitted to AFCD and EPD, summarizing the
monitoring results with key findings of the dry season monitoring conducted in
December 2023 and January 2024.
Wet season
monitoring of ichthyoplankton was conducted using plankton net on 23 August
2024 while monitoring of juvenile fish was conducted using purse seine on 26
and 27 August 2024. Monitoring is conducted for at least 3
years after the completion of eco-shoreline, twice in wet season and twice in
dry season, while ichthyoplankton and juvenile fish monitoring will be
conducted on a monthly basis covering May to August
for at least 3 years, in order to determine the effectiveness of the
eco-shoreline in accordance with the Updated EM&A Manual and Eco-shoreline
Implementation Plan.
No post-construction soft shore
ecological monitoring at Tung Chung Bay and Tai Ho Wan was scheduled during the
reporting period. The post-construction soft shore ecological monitoring
at Tung Chung Bay and Tai Ho Wan was scheduled to be conducted in September
2024 in accordance with the Updated EM&A Manual.
Site
inspections were carried out on a weekly basis with the Contractor and ER to
monitor the implementation of proper environmental pollution control and
mitigation measures for air quality, noise, water quality, waste management,
marine ecology, landscape and visual impacts and preservation and/or
transplantation of plant species of conservation importance under the
Project. In the reporting period, two (2) site inspections were carried
out on 1 and 8 August 2024 for Contract 1, four (4) site inspections were
carried out on 7, 14, 21 and 28 August 2024 for Contract 2, five (5) site
inspections were carried out on 2, 9, 14, 23 and 30 August 2024 for Contract 3
and four (4) site inspections were carried out on 6, 13, 20 and 27 August 2024
for Contract 7.
Key
observations during the site inspections are summarized in Table 2.7.
Table 2.7 KEY
Observations Identified during the Site Inspection in this Reporting
Month
Contract No. |
Inspection Date |
Environmental Observations |
Recommendations/ Remarks |
1 and 8 August 2024 |
Area G • No deficiency was observed. |
• Nil. |
|
Contract 2 |
7 August 2024 |
Portion 5 • General refuse was observed on ground.
|
Portion 5 • The Contractor was reminded to remove the refuse and maintain good housekeeping.
|
14 August 2024 |
Portion 3 • No deficiency was observed. |
• Nil.
|
|
21 August 2024 |
Portion 3 • Insufficient drainage control was observed.
• Exposed stockpile was observed.
Portion 6 • Insufficient drainage control was observed. |
Portion 3 • The Contractor was urged to critically review the drainage / water divert system to prevent runoff.
• The Contractor was reminded to properly cover up the exposed stockpile.
Portion 6 • The Contractor was urged to critically review the drainage / water divert system to prevent runoff. |
|
28 August 2024 |
Portion 3 • Insufficient drainage control was observed.
• Exposed stockpile was observed.
|
Portion 3 • The Contractor was urged to critically review the drainage / water divert system to prevent runoff.
• The Contractor was reminded to properly cover up the exposed stockpile. |
|
Contract 3 |
2 August 2024 |
Portion 7, 10, 16b, 104, TTA • No deficiency was observed. |
• Nil. |
9 August 2024 |
Portion 16b • Dust was observed from cement mixing.
• Accumulated general refuse was observed on ground.
Road L8 • Chemical container was observed placing on the ground. |
Portion 16b • The Contractor was reminded to mix concrete in an area sheltered on the top and the 3 sides to minimize dust nuisance.
• The Contractor was reminded to remove waste and maintain a good housekeeping.
Road L8 • The Contractor was reminded to provide drip tray for chemical to avoid spillage.
|
|
Portion 8 • Appropriate non-Road Mobile Machinery (NRMM) label was not observed on generator.
• Accumulated refuse was observed on ground. |
Portion 8 • The Contractor was reminded to affix appropriate NRMM labels in accordance with the Air Pollution Control (Non- Road Mobile Machinery) (Emission) Regulation.
• The Contractor was reminded to remove waste and maintain a good housekeeping. |
||
23 August 2024 |
CUT • Appropriate Non- Road Mobile Machinery (NRMM) label was not observed on generator. |
CUT • The Contractor was reminded to affix appropriate NRMM labels in accordance with the Air Pollution Control (Non- Road Mobile Machinery) (Emission) Regulation.
|
|
30 August 2024 |
Portion 16a, 16b, 104, TTA • No deficiency was observed. |
• Nil. |
|
Contract 7 |
6 August 2024 |
Portion 146 • Appropriate Non- Road Mobile Machinery (NRMM) label was not observed on generator.
• Oil stain was observed on ground.
Main Haul Road
• Dry and dusty haul road was observed. |
Portion 146 • The Contractor was reminded to affix appropriate NRMM labels in accordance with the Air Pollution Control (Non- Road Mobile Machinery) (Emission) Regulation.
• The Contractor was urged to clean the oil stain and rectify the situation immediately.
Main Haul Road • The Contractor was reminded to provide adequate dust mitigation measures, such as watering. |
13 August 2024 |
Portion 146 • No deficiency was observed. |
• Nil. |
|
20 August 2024 |
Portion 30, R7 • No deficiency was observed. |
• Nil. |
|
27 August 2024 |
Portion 146 • General refuse was scattered on ground. |
Portion 146 • The Contractor was reminded to remove the refuse and maintain good housekeeping. |
The Contractors
have rectified all of the observations identified
during environmental site inspections in the reporting period. The Contractors were reminded to implement all
relevant mitigation measures related to construction dust, construction noise,
water quality and waste management outlined in the EIA Report and Updated
EM&A Manual.
The Contractors of Contract 1, 2, 3
and 7 have registered as chemical waste producer. Sufficient
numbers of receptacles were available for general refuse collection and
sorting.
All dump trucks engaged on site was
equipped with RTTM system during the reporting period. The Surveillance
Team of the ET conducted regular site inspection on the dump trucks and their
track records. No illegal dumping and landfilling of C&D materials
was found during the reporting period.
Wastes generated during this
reporting period include mainly non-inert construction wastes. Reference
has been made to the waste flow tables prepared by the Contractors. The
quantities of different types of wastes and imported fill materials are summarised in Table 2.8.
Table 2.8 QUANTITIES
OF Different Waste Generated and Imported Fill Materials
Contract No. |
Month/ Year |
Inert C&D Materials a (m3) |
Imported Fill b (sand) (m3) |
Imported Fill c (public fill) (m3) |
Inert Construction Waste Re-used d (m3) |
Non-inert Construction Waste e (m3) |
Recyclable Materials f (kg) |
Chemical Wastes (kg) |
TCNTE (East) |
1 to 30 Jun 24 |
0.0 |
0.0 |
0.0 |
1,755.0 |
285.9 |
0.0 |
0.0 |
1 to 31 Jul 24 |
0.0 |
0.0 |
0.0 |
506.0 |
320.7 |
450.5 |
0.0 |
|
1 to 31 Aug 24 |
0.0 |
0.0 |
0.0 |
5,160.4 |
656.7 |
0.0 |
0.0 |
Note:
a Inert construction wastes include hard
rock and large broken concrete, and materials disposed as public fill.
b Imported
materials include of sand fill from any source outside of TCNTE.
c
Imported sorted public fill include all G200, G400 and glass gullet (local
recycling materials) from any source outside of TCNTE.
d
Reuse of inert construction waste generated under the TCNTE contracts.
e Non-inert construction wastes include general refuse
disposed at landfill.
f
Recyclable materials include metals, paper, cardboard, plastics
and others.
Implementation of applicable
landscape and visual mitigation measures was monitored in accordance with the
Updated EM&A Manual. All measures undertaken by the Contractor during
the construction phase and establishment work phase shall be audited by ET to
ensure compliance with the intended aims of the measures.
The implementation status of the
environmental protection measures is summarized below in Table 2.9.
Examples of landscape and visual mitigation measures are presented in Annex J1. The
monitoring programme for detailed design,
construction and establishment stages is presented in Table 2.10.
Event and Action Plan for Landscape and Visual impacts is stated in Annex J2.
Table 2.9 IMPLEMENTATION
STATUS of Landscape and Visual Mitigation Measures
Landscape and Visual Mitigation Measures during Construction |
Implementation Status |
Relevant Contract(s) in the Reporting Period |
MM1 – Optimization of Construction Areas & Providing Temporary Landscape on Temporary Construction |
Implementation of the measures were carried out during the detailed design stage of the Project. |
NA
|
MM2 – Minimize Topographical Changes |
Implementation of the measures were carried out during the detailed design stage of the Project. |
NA |
MM3 – Preservation of Potentially Registerable OVTs, Rare and Protective Vegetation |
Tree Protection Specifications were provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project. The Contractors submitted Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance under EP condition 2.21. The Contractors’ performance on the implementation of the tree maintenance and protection measures were observed and checked by the ET weekly during construction period. |
All works contracts |
MM4 – Transplanting of Existing Trees
|
Tree Transplanting Specifications were provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project where trees would unavoidably be affected by the construction works. The Contractors submitted Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance under EP condition 2.21. The transplanted plant species of conservation importance were both certified as dead trees by the QP on 15 June 2022 as no living signs were observed. |
Contract 2 |
MM5 – Screen Hoarding
|
All works contracts |
|
MM6 – Adopting Non-dredge Method for the Reclamation |
Not applicable during the reporting period. |
NA |
MM9 – Providing Natural Rock Material/ Planting for Artificial Seawall |
Rock armour reused and construction of eco-shoreline (mangrove eco-shoreline, rocky eco-shoreline and vertical eco-shoreline) in progress. The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
Contract 1 |
MM10 – Compensatory Planting |
Not applicable during the reporting period. |
NA |
MM11 – Woodland Restoration |
The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
Contract 2 |
MM12 – Screen Planting |
Not applicable during the reporting period. |
NA |
MM13 – Roadside Planting |
Not applicable during the reporting period. |
NA |
MM14 – Aesthetic Design of Built Development |
Not applicable during the reporting period. |
NA |
MM15 – Maximise Greening on Structures |
Not applicable during the reporting period. |
NA |
MM16 – Noise Barrier Design |
Not applicable during the reporting period. |
NA |
MM18 – Landscaping on Slopes |
Not applicable during the reporting period. |
NA |
MM20 – Lighting Control |
The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
All works contracts |
Table 2.10 MONITORING Programme for Landscape and
Visual
Stage |
Monitoring Task |
Monitoring Report |
Form of Approval |
Frequency |
Design |
Monitoring of design works against the recommendations of the landscape and visual impact assessments within the EIA should be undertaken by the Engineer and Landscape Architect, to ensure that they fulfil the intentions of the mitigation measures. Any changes to the design, including design changes on site should also be checked |
Report by CEDD / ER confirming that the design conforms to requirements of EP. |
Approval by Project Proponent |
At completion of design stage |
Construction |
Monitoring of the contractor’s operations during the construction period. |
Report on Contractor's compliance by ET |
Counter-signature of report by IEC |
Monthly |
Establishment Works |
Monitoring of the planting works during the 24-months Establishment Period after completion of the construction works. |
Report on Contractor's compliance by ET |
Counter-signature of report by IEC |
Bi-monthly |
A summary of
the Environmental Mitigation Implementation Schedule is presented in Annex B. The necessary
mitigation measures were implemented properly for the Project.
There was no
notification of summons or prosecution recorded in the reporting period.
One (1) environmental complaint related to Contract 2 and
Two (2) environmental complaints related to Contract 3. Investigations were
conducted for the environmental complaint in accordance with the complaint
handling process as stated in the Complaint Management Plan.
Environmental complaints in the reporting period are summarized below.
|
Complaint(s) |
Investigation/Follow up action(s) |
1
|
Environmental complaint related to Contract 3 regarding dust nuisance for construction vehicles moving in and out of the Tung Chung East Development Area was received on 6 August 2024 and referred by EPD on the same day. |
Based on the information provided by the Contractor with confirmation from RSS, water trucks and road sweepers have been deployed to clean Ying Hei Road (between Ying Tung Estate and Yi Tung Road) at least five time on each working day for dust control. Based on ET’s regular inspection, wheel washing facilities were installed and operated at the exit gate of the TCE reclamation area for a thorough cleanse of car wheel before leaving the site. In addition, there are other construction sites nearby, which could also be potential contributors to the mentioned dust. Nevertheless, the Contractor provided morning brief to workers and foreman regarding dust control. |
2 |
Environmental complaint related to Contract 2 regarding unpleasant smell near Tung Chung North Park and Ling Liang Church Sau Tak Primary School was received on 19 August 2024 and referred by EPD on 22 August 2024. |
A joint site inspection was conducted with RSS, Contractor, IEC, and ET on 28 August 2024. No unpleasant smell was detected. Nevertheless, the Contractor stopped the usage of the concerned generator and placed the new generator further away from Tung Chung North Park to minimize any potential air nuisance. |
3 |
Environmental complaint related to Contract 3 regarding water quality was received on 19 August 2024 and referred by EPD on 28 August 2024. |
A joint site inspection was conducted with Contractor and EPD on 27 August 2024. No muddy water nor illegal discharge was observed. According to information provided by the Contractor with confirmation from RSS, only Area 5 Stream E would discharge treated water to the related box culvert and the wastewater treatment system in place was in normal operation on the complaint date. In addition, the Amber Rainstorm Signal was hoisted on 15 August 2024 by the Hong Kong Observatory, and since the box culvert have already been connected to the public drainage system, muddy water from Tung Chung areas apart from Tung Chung East construction site might also rush into storm drains and discharge into the sea. The water quality issue was unlikely to be related to the Project. |
Statistics on complaints, notifications of
summons, successful prosecutions are summarised in Annex K.
Works to be undertaken in the
next monitoring period of September 2024 are summarized in Table 3.1
below, together with the key issues and the key mitigation measures:
Table 3.1 Major
Activities for the Next Reporting Period
Activities |
Key Issues |
Key Mitigation Measures |
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
||
Land-based Works |
||
• Removal of siltation at IORC
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Potential surface runoff · Noise from plant operation during normal working hours or restricted hours · Dust emission during storage and transfer of sand/ sorted public fill |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Strictly follow requirement under CNP for the use of PMEs and works within restricted period · Use of acoustic mat and other noise mitigation measures when necessary · Regular maintenance of engines and mechanical equipment |
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
||
Land-based Works |
||
· Construction of pumping station at Portion 6 · Construction of Intake Culvert at Portion 6 · Construction of service reservoir, TMF mainlaying at Portion 3 · Construction of HDD works at Portion 3 · Watermain laying works at Portion 3 along Man Tung Road, Tung Chung Road and inside WSD facilities · Watermain laying works at Yi Tung Road at Portion 4 · Manhole construction and pipe laying for drainage works at Portion 5A · Construction of T-Junction in Yi Tung Road at Portion 5 |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
||
Land-based Works |
||
· Excavation and ELS works at Portion 104 · Excavation and ELS works at CUT no.1, 2, 3, 4 and supporting building · Construction works for CUT no. 1 structure · Back-filling works for CUT 2 · Construction works and furniture installation of PM office at WA9 · Construction works of Contractor office at WA6 · Drainage, Sewerage and watermain works at Road L4, L3, L5 and Portion 16 · DCS works at Road L4 and L3. · Pipe laying works for twin rising mains/ watermain laying at Man Tung Road · Preparation and pipe jacking works at Ying Tung Road · Pipe jacking works at Yi Tung Road · Foundation and backfilling works for noise barrier at Portion 11 · Road and drainage works in Road P1 · Road widening works at Ying Hei Road · Road D4, Road L7, ELS installation |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management |
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
||
Land-based Works |
||
· Open cut excavation, backfilling and pipe laying for rising main and watermain at Portion 146-1 to 146-5 · Pak Mong bridge I-beam erection, insitu construction of abutment and diaphragm · Trench excavation and pipe laying works at Portions 32 (Sham Shui Kok Drive) and Portion 38 · Trench excavation and pipe laying works at Portion 32 (Access Road adjacent to MTRC Siu Ho Wan Depot) · Establishment of pipe jacking works at Portion 33 · Horizontal grouting at Receiving pit at Portion 32 · RC construction of Retaining Wall FR1 · Pak Mong Subway Extension Phase 1 Temporary Pedestrian Diversion · Preparation works for falsework at casting yard A1 and A2 · ELS at A1a and A2b · RC for RW-R1, RW-R2, RW-R3 and RW-R4 at Portion 146-2 to 146-4 · RC construction at RW-R7 at Portion 31 · RC works at Wall E · Mini-piles at Wall D · Bored piles at Bridge C at Portion 146-12 · U channel and chain link fence construction at Portion 147-1 and 147-2 · Site clearance and tidiness |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
The ET will keep track on the construction
works to confirm compliance of environmental requirements and the proper
implementation of all necessary mitigation measures. The ET will also
recommend to the Contractors about the environmental toolbox topics on the
abovementioned key issues for the next reporting period.
The tentative schedules for
environmental monitoring in September 2024 are provided in Annex L.
This
EM&A Report presents the findings of the EM&A activities undertaken for
the TCE Project during the period from 1 to 31 August 2024 in accordance with
the Updated EM&A Manual and the requirements of the Environmental Permit (EP-519/2016).
Air
quality (1-hour TSP), noise, eco-shoreline, compensation woodland, in-situ
preserved plant species of conservation importance and transplanted plant
species of conservation importance were carried out in the reporting
period.
The
monitoring results for air quality monitoring (1-hour TSP) complied with the
Action/ Limit levels in the reporting period.
No
exceedance of Action/Limit Level was recorded for construction noise monitoring
in the reporting period.
Water
quality monitoring was suspended in the reporting period.
Mangrove
eco-shoreline, rocky eco-shoreline and vertical eco-shoreline were
completed. Wet season monitoring was conducted during the reporting
period.
No
post-construction soft shore ecological monitoring at Tung Chung Bay and Tai Ho
Wan was conducted during the reporting period.
No
compensation woodland monitoring was carried out in the reporting month.
Monitoring
of the in-situ preserved plant species of conservation importance and
monitoring of the transplanted plant species of conservation importance were
carried out in the reporting period.
Environmental
site inspections were carried out during the reporting period.
Recommendations on remedial actions were given to the Contractors for the
deficiencies identified during the site inspections.
There
were no notification of summons or prosecution recorded in the reporting
period. One (1) environmental complaint related to Contract 2 and Two (2)
environmental complaints related to Contract 3. Investigations were
conducted for the environmental complaint in accordance with the complaint
handling process as stated in the Complaint Management Plan.
The ET
will keep track on the construction works to confirm compliance of
environmental requirements and the proper implementation of all necessary
mitigation measures.
([1])
ERM (2018a). Updated Environmental Monitoring and Audit Manual for
Tung Chung New Town Extension. Deposited to EPD under EP-519/2016
([2])
Arup (2015). Environmental Impact Assessment Report for Tung Chung
New Town Extension. Deposited to EPD under Register No. AEIAR-196/2016